Hi All,
I am using Power BI connected to Project Online to report on Project progress. I would like to start measuring/reporting on changes to the Project Finish date. The Finish Date does come through on the Project Baselines table however it is hard to map a nice visual trend as there appears to be no Baseline Create Date.
Assuming the Baseline Create date does exist in Project Online, does anyone know how you can pull this field through into Power BI?
Thanks,